Costa del Sol is now one of the most promising areas for real estate investments. The region attracts both international investors and those seeking the perfect place to live. Modern residential complexes with luxurious amenities, improved infrastructure, and proximity to the sea make Estepona a unique choice. The area is undergoing rapid development, with numerous new residential projects offering cutting-edge designs and high-quality finishes.
One of these projects is our Bougainvillea complex, offering 25 middle+ segment apartments, designed with comfort and style in mind, and equipped with the latest amenities for modern living.
The beginning of construction
The construction permit for the Bougainvillea residential complex was received in 2024. Construction work began in January 2025.
March 2025
Foundation work was commenced at the construction site. Excavators were used to prepare the ground by removing excess soil and leveling the surface. Reinforcement grids were installed in the prepared forms, and formwork was set up for the concrete pour.
The final stage involved preparing for the concrete pouring to solidify the foundation. These tasks are essential for creating a strong base for the building.
Formwork is installed to shape and contain the concrete, while reinforcement bars are arranged to provide strength
Concrete will then be poured into the formwork to create a solid foundation, ensuring the stability and longevity of the structure.
April 2025
May 2025
Excavation and groundwork are complete, with reinforcement and concrete pouring underway for the foundation and walls.
Building materials are on-site, ensuring continued progress in the upcoming phases.
The building structure already taking shape. In the latest phase, the concrete for the walls is being poured, and the framework is now fully in place.
Workers are continuing to reinforce the construction with the necessary materials, ensuring a solid and reliable foundation.
June 2025
The crane remains active, assisting with the transportation of materials to higher levels of the structure. The team is diligently working to complete the next stages of the construction, and the building is beginning to take its final form.
The overall progress indicates a promising outlook for the timely completion of this luxurious development.
July 2025
SHOWFLAT OFFICE
Since July 2025, the company has opened an office for client meetings just 500 meters away from the construction site.
In the office, you can explore the finishing options and design projects for each of the 25 apartments. A personal manager will be assigned to you for prompt communication regarding any questions you may have.